Baurecht
Latest

Assessing connected projects together: project clusters and EIA thresholds

Project clusters and EIA thresholds: how connected similar projects are assessed together and determination documents are prepared.

BRANDAUER Rechtsanwälte
Your law firm

BRANDAUER Rechtsanwälte

Salzburg law firm for real estate, construction and corporate law

Every matter is handled by a coordinated team of lawyers, legal staff and specialists. In construction cases we look at contract, evidence, deadlines and commercial consequences together.

19 September 2026 · Mag. Bernhard Brandauer, Rechtsanwalt

Several projects may be relevant together when EIA thresholds are assessed. The key questions are whether similar projects are spatially connected and which projects already exist, have been approved or were previously submitted with a complete application.

Section 3(7) of the Austrian Environmental Impact Assessment Act 2000 allows the authority to determine whether an environmental impact assessment is required and which statutory threshold category is realised. The project applicant must provide documents that identify the project and allow its environmental impacts to be assessed.

This article explains project clusters, cumulative threshold assessment and the route to an authority determination. The individual building permit, other specialist approvals and the substantive approval procedure after the assessment remain separate questions.

Classify the project

What should be clarified first when projects are connected?

Three questions lead from the project structure to a focused preparation of the authority determination.

Already know you want to get in touch? Go straight to the enquiry form.

01 Question 1

Are there several similar projects with a spatial connection?

Include projects that already exist, have been approved or were previously submitted with a complete application.

All paths at a glance

Overview of all answers.

01

For an independent project, start with the relevant EIA category and its threshold.

Describe the type, scope, capacity and location of the project. Then check whether similar projects exist in a spatial connection or were previously submitted in full.

02

An unclear procedural status prevents a reliable comparison of the projects.

For each project, record the site, type, capacity, approval status and filing date. Secure decisions and complete applications before comparing the thresholds.

03

Missing site, capacity or impact information should be completed before the determination request.

Collect the project description, site documents, capacity data and available information on soil, water, land, waste and emissions. Clearly mark open points.

04

A clearly documented project cluster can provide the basis for an authority determination.

Present project parts, comparison projects, capacities and spatial connections in one consistent overview. Add the documents needed to estimate environmental impacts and formulate the determination question clearly.

When projects are assessed together

For cumulative assessment under Section 3(2) of the Environmental Impact Assessment Act 2000, other similar projects with a spatial connection must be considered. The relevant view is therefore the complete project structure at the affected site. Splitting a project into separate construction stages does not answer the project-cluster question by itself.

Projects that already exist or have been approved are included. The Act also refers to projects that were previously submitted to an authority with a complete application for approval or were previously applied for under Sections 4 or 5.

The comparison should show which project belongs to the applicant, which projects are spatially connected, which capacity is relevant and what status each comparison project has. This overview provides the basis for the threshold assessment.

How the threshold is assessed across a project cluster

A project that does not reach a threshold on its own may still be relevant when assessed together with other similar projects. The authority then determines in the individual case whether cumulative impacts are expected to have significant harmful, disturbing or adverse effects on the environment.

The applicant should therefore present the capacity of the proposed project and the capacities of the relevant projects using the same unit and the same boundary. Different project stages or technical descriptions should not make the comparison unclear.

Section 3(2) contains a lower limit for the individual-case assessment: it is not carried out where the proposed project has less than 25 percent of the threshold. This statement concerns the individual-case assessment regulated there and does not settle other EIA categories.

How to prepare the authority determination

Under Section 3(7) of the Environmental Impact Assessment Act 2000, the project applicant may request a determination on whether an EIA is required and which category in Annex 1 or Section 3a(1) to (3) is realised. A participating authority or the environmental ombudsman may also request it, and the authority may act on its own initiative.

The project applicant must provide documents sufficient to identify the project and estimate its environmental impacts. Where an individual-case assessment is required, the authority limits the depth and scope of its review to a preliminary assessment. The procedure is therefore not a substitute for a complete technical environmental assessment.

The decision must be issued by formal decision within six weeks. A clear request should bring together the project description, site, spatial connection, capacities, existing or approved projects and expected impacts in a readable file.

What matters before the assessment is complete

For projects subject to an assessment under Section 3(1), (2), (4) or (4a), approvals may not be granted before the EIA or individual-case assessment is complete. Notifications made under administrative provisions have no legal effect before completion.

This consequence makes the timing of the project-cluster assessment important. The applicant should establish whether the project is already subject to an assessment, which documents are available and which authority is responsible for the determination or individual-case assessment.

The project-cluster question is separate from substantive approval. The first step is to establish whether and to what extent the Environmental Impact Assessment Act applies. The individual approval requirements under the applicable rules are then assessed.

Which project file makes the comparison reliable

A reliable project file contains a site plan showing spatial connections, a description of the entire project and a list of its parts. For each project, the type, technical features, capacity, approval status and filing date should be identifiable.

Available information on the environmental areas likely to be affected should be added. Depending on the project, this may include soil, land, water, biodiversity, waste, emissions and the use of natural resources. Open data points should be marked as such.

Before filing, applicants should review the threshold calculation, the spatial boundary and the determination question together. A consistent presentation helps the authority conduct its preliminary assessment and prevents relevant project parts from appearing only in separate documents.

Review levels

Three levels of an EIA pre-assessment

Project structure, threshold and determination answer different questions.

Project clusters and thresholds before filing
Review level Core question Key documents
Project cluster Which similar projects are spatially connected? Site plan, project list, status and filing dates
Threshold Which capacities must be compared together? Units, capacity data, threshold and calculation
Determination Is an EIA or individual-case assessment required? Project description, site and impact estimate

The specific classification depends on the EIA category, project features and applicable statutory requirements.

Procedure

Five steps for an orderly project assessment

One file keeps project structure, cumulative assessment and determination distinct.

  1. 01
    Step 1

    Describe the entire project

    Record project parts, site, purpose and technical features in one overview.

  2. 02
    Step 2

    Identify comparison projects

    Include existing, approved and previously submitted similar projects.

  3. 03
    Step 3

    Compare capacities

    Set out threshold, unit and cumulative capacity in a verifiable way.

  4. 04
    Step 4

    Estimate impacts

    Describe site, resources, emissions and expected environmental impacts.

  5. 05
    Step 5

    Prepare the determination

    Align the question and documents with the authority and project cluster.

Practical note: Give each project and comparison project its own line with site, capacity, status and filing date. Receive new articles and legal information through BRANDaktuelle Rechtsnews.

FAQ

Project clusters and EIA thresholds

What is a project cluster for EIA threshold assessment? +

It refers to similar projects with a spatial connection that may be relevant for cumulative assessment. Under Section 3(2), existing or approved projects and certain projects previously submitted in full may be considered.

Are only projects planned at the same time assessed together? +

No. In addition to the proposed project, similar projects may be included if they already exist, have been approved or were previously submitted with a complete application or applied for under Sections 4 or 5.

What does the 25 percent limit mean? +

Under Section 3(2), the individual-case assessment regulated there is not carried out where the proposed project has less than 25 percent of the threshold. This does not finally determine other EIA categories.

Who may request a determination under Section 3(7)? +

The project applicant, a participating authority or the environmental ombudsman may request the determination. The authority may also act on its own initiative. The decision is issued formally.

Can an approval be granted before a required assessment is complete? +

For projects subject to an assessment under Section 3(1), (2), (4) or (4a), an approval may not be granted before completion. Notifications under administrative rules have no legal effect until then.

Topics
Project clusterEIA 2000EIA thresholdsEnvironmental impact assessmentConstruction project

Defects, a remuneration dispute, looming litigation?

In construction law, deadlines and evidence decide. Call us directly or send an email, callback within one business day.

Contact

A direct line to the firm.

Address

BRANDAUER Rechtsanwälte GmbH Giselakai 51 5020 Salzburg