Baurecht
Construction contract

Extension of time and delay notices: preliminary works and schedule

When construction dates slip, delay notice, preliminary works and schedule must be checked before costs and penalties escalate.

BRANDAUER Rechtsanwälte
Your law firm

BRANDAUER Rechtsanwälte

Salzburg law firm for real estate, construction and corporate law

Every matter is handled by a coordinated team of lawyers, legal staff and specialists. In construction cases we look at contract, evidence, deadlines and commercial consequences together.

6 July 2026 · Mag. Bernhard Brandauer, Rechtsanwalt

Construction delay often becomes visible only when the completion date is at risk. The cause is frequently earlier: missing preliminary works, late decisions or trades that are not coordinated.

Extension of time and delay notice should therefore be separated from the pure penalty topic. Before sanctions, the question is who actually influenced the sequence.

This article supplements the existing guide on delay and penalties. It focuses on the narrower situation where dates slip because of preliminary works, cooperation duties or sequence disruptions.

Assess your situation

What is the next sensible step?

Answer two short questions. You receive an initial orientation on documents and reactions that matter now.

Already know you want to get in touch? Go straight to the enquiry form.

01 Question 1

What is the main issue right now?

The assessment helps distinguish prevention, evidence and response.

All paths at a glance

Overview of all answers.

01

Before a binding statement, risk can usually be managed best.

Check the contract, permits, plans and intended statement before signing, approving or continuing works.

This preserves evidence, negotiating position and practical options.

02

With complete documents, the legal position can be assessed precisely.

If a dispute already exists, chronology and records matter. They determine whether payment, reservation, repair or enforcement is sensible.

The key is the connection between contract, actual progress and documented statements.

03

Missing evidence should be preserved first.

If documents are missing, request and secure them immediately.

Photos, minutes, emails and invoices help make the facts reliable.

Distinction from penalties and completion delay

A penalty concerns the legal consequence of missing a date. A delay event concerns the cause why a date cannot be met.

Anyone looking only at the contractual penalty often misses the prior question of cooperation, preliminary works and sequence planning.

This article therefore does not assess the amount of a penalty, but the documentation of disruption.

Which preliminary works influence the schedule

Preliminary works may include plans, approvals, samples, access, power, water, scaffolding or completed works by other trades.

If a prerequisite is missing, the contractor cannot always simply continue. Conversely, the contractor must not assert disruption in a vague way.

The decisive point is whether the missing prerequisite is described specifically and is truly relevant for the schedule.

Why a delay notice must be specific

A mere statement that delays exist is often not enough. Cause, timing, affected works and impact are needed.

If ÖNORM B 2110 was agreed, contractual notice and documentation duties may be particularly important. Without such agreement, the contract and general works contract law apply.

Clients should check each notice for plausibility, evidence and causal link to the requested extension of time.

The schedule as evidence, not just a calendar

A schedule is more than a wish list. It shows dependencies between trades and makes visible which activity affects the critical path.

If the schedule is never updated, it is of limited help in a dispute. Changes, approvals and disruption should be entered continuously.

This later helps assess whether a delay truly follows from the alleged cause.

How clients should react to shifted dates

Request a concrete explanation of the cause, affected works and alleged additional time. Vague weekly estimates are rarely enough.

At the same time, check your own cooperation duties. If a decision or approval is missing, it should be provided quickly and documented.

For larger projects, a joint progress meeting with minutes is useful so that the parties do not later dispute the status at the time.

Schedule review

What to separate in extension of time issues

The table shows which questions should be clarified before costs and penalties.

Assessment of disruption and schedule
Point To check Why it matters
Cause Which prerequisite is missing Causation for additional time
Notice Timing and content Evidence of timely reaction
Schedule Critical path Impact on completion

An extension of time should never be asserted only in general terms.

Process

Document shifted dates properly

A short sequence helps with evidence and response.

  1. 01

    Name the disruption

  2. 02

    Check impact

  3. 03

    Secure response

Practical tip: Separate shifted dates from cost claims. Only after cause, impact and sphere of responsibility are documented can additional time be assessed legally. Book an initial consultation (72 euros)

FAQ

Extension of time and delay notice.

Is a simple email enough for a delay notice? +

An email can matter in practice. It should specify cause, timing, affected works and alleged impact.

Do I have to accept every extension of time? +

No. Check whether the cause is evidenced and whether it actually affects the schedule. General statements should be questioned.

What role does ÖNORM B 2110 play? +

It does not apply automatically, only if agreed. If agreed, notice and documentation may be particularly important.

Topics
Extension of timeDelay noticeSchedulePreliminary worksConstruction contract

Defects, a remuneration dispute, looming litigation?

In construction law, deadlines and evidence decide. Call us directly or send an email, callback within one business day.

Contact

A direct line to the firm.

Address

BRANDAUER Rechtsanwälte GmbH Giselakai 51 5020 Salzburg