Unlawful building decision: revocation or amendment under section 68 AVG

When a final building decision may be revoked or amended ex officio under section 68 AVG and how finality limits that power.

BRANDAUER Rechtsanwälte
Your law firm

BRANDAUER Rechtsanwälte

Salzburg law firm for real estate, construction and corporate law

Every matter is handled by a coordinated team of lawyers, legal staff and specialists. In construction cases we look at contract, evidence, deadlines and commercial consequences together.

30 September 2026 · Mag. Bernhard Brandauer, Rechtsanwalt

A final building decision can still be revoked or amended ex officio under the narrow conditions of section 68 of the General Administrative Procedure Act. The provision protects finality while preserving specific correction powers for the authority.

The first question is whether anyone has acquired a right from the decision. The next questions are whether the case falls under the rule for decisions without acquired rights, an exceptional public-interest situation or a statutory ground of nullity.

This article classifies ex officio correction of a building decision. It distinguishes that route from an appeal against a decision that is still open, reopening for new facts and evidence, and a building-police order.

Classify your situation

Can a final building decision be corrected ex officio?

Three questions show whether an ordinary remedy, a section 68 assessment or another procedure should come first.

Already know you want to get in touch? Go straight to the enquiry form.

01 Question 1

Has the building decision become final?

While an ordinary legal remedy remains available, that remedy must be examined first.

All paths at a glance

Overview of all answers.

01

While an ordinary legal remedy remains available, that procedure comes first.

Secure the decision, proof of service and information on legal remedies. The overview of appealing a building decision addresses this earlier procedural situation.

02

If nobody acquired a right from the decision, section 68(2) may allow ex officio correction.

Classify the decision, its legal effects and the competent authority. Under the statutory conditions, the issuing authority or the supervisory authority may revoke or amend such a decision.

03

For a decision that grants a right, section 68(3) requires a particularly narrow public-interest assessment.

Document the specific danger or serious economic harm and explain why correction is necessary and unavoidable. Acquired rights must be protected as far as possible.

04

A declaration of nullity under section 68(4) requires one of the grounds expressly listed there.

Check the authority’s jurisdiction, the composition of a collegiate authority, practical feasibility and errors that legislation expressly treats as void. A general suspicion of unlawfulness is not enough.

05

Dissatisfaction with a final building decision does not create a free-standing power of later correction.

Separate ex officio correction from an appeal, reopening and a building-police order. A reliable classification requires the complete decision and the procedural file.

What section 68 means for a final building decision

Section 68 concerns decisions that are no longer subject to an ordinary appeal. An open legal remedy must therefore be distinguished from a later ex officio correction. The article on appealing a building decision covers that earlier situation.

Subsection 1 generally requires an application by a party seeking to amend a final decision to be rejected as res judicata unless the authority finds grounds for action under subsections 2 to 4. The provision does not create a general right to a new merits decision.

For a building project, the operative part of the decision matters. An alleged technical error, a later change to the plans or a dispute about execution may belong to another procedure depending on the objective.

When subsection 2 permits correction without an acquired right

Under section 68(2), a decision from which nobody has acquired a right may be revoked or amended by the authority that issued it. The same can occur through supervision by the competent superior authority.

The assessment therefore starts with the legal effect of the specific decision. It must be established whether a right was granted, confirmed or already used by a person. Calling a document a building permit does not answer that question for every procedural stage.

The provision does not give the authority a free power to change every inconvenient or later unwanted decision. Jurisdiction, the content of the decision and the absence of an acquired right must be traceable from the file.

How subsection 3 limits correction where rights were acquired

Under section 68(3), other decisions may be amended in the public interest only to the extent necessary and unavoidable to remove conditions endangering human life or health or to prevent serious economic harm.

The competent authority is the authority that issued the decision at last instance or the competent superior authority. This is substantially narrower than a general later review of a building permit.

Section 68(3) also requires acquired rights to be protected as far as possible. For building owners, neighbours and other parties, the concrete legal position affected and the reason why the correction remains necessary must therefore be identified.

When a declaration of nullity under subsection 4 may apply

Section 68(4) permits the competent superior authority to declare a decision void through supervision where it was issued by an incompetent authority or an improperly composed collegiate authority, would produce a criminal-law result, is factually impossible to implement or suffers from an error that legislation expressly treats as void.

These grounds must be assessed separately. An ordinary substantive error, an unattractive planning solution or a later change in interests does not by itself establish nullity.

For the ground concerning an incompetent authority, subsection 5 imposes a time limit. After three years from the point referred to in section 63(5), a declaration of nullity on that ground is no longer available. The relevant starting point must be established from the file.

Distinguish the procedures

Which route fits the situation?

The finality of a building decision does not by itself identify the correct procedure for the underlying problem.

Ex officio correction and neighbouring procedures
Route Starting point Key question
Section 68 Final decision and a possible statutory correction ground Is there a case under subsection 2, 3 or 4?
Appeal The decision can still be challenged by an ordinary remedy Which deadline, objections and legal effects apply?
Reopening Concluded proceedings and a statutory reopening ground Did new facts or evidence emerge later without the party’s fault?
Building-police order The authority addresses an unlawful condition or ongoing works What action does the authority require and how should it be addressed?

The correct classification depends on the decision, the file and the concrete objective of the person affected.

Practical steps

Organise the file in five steps

A clear chronology shows whether the issue concerns finality, an acquired right or a special statutory ground.

  1. 01
    Step 1

    Secure decision and service

    Collect the complete decision, proof of service and information on remedies

    Keep attachments, plans and later corrections with the decision. Its exact content is the basis for every further assessment.

    Legal basis: Section 68 AVG

  2. 02
    Step 2

    Establish finality

    Separate an open appeal from remedies that have already been decided

    Record service, expiry of the deadline and every decision in the remedy proceedings. An open remedy changes the starting point.

  3. 03
    Step 3

    Assess legal effects

    Record whether the decision granted a right to anyone

    Assign beneficiaries, implementation steps and affected neighbour positions on the basis of the file.

  4. 04
    Step 4

    Narrow the section 68 ground

    Compare subsections 2, 3 and 4 with their separate requirements

    For subsection 3, document public interest, necessity and unavoidability. For subsection 4, identify a specific ground of nullity.

  5. 05
    Step 5

    Clarify authority and effects

    Derive the authority, affected rights and next steps from the complete file

    Record which decision is challenged, who could change it and how correction would affect the building project.

The complete file matters: Keep the decision, service, plan version, remedies, implementation and affected legal positions together. Withdrawal or amendment of a pending building application is separate and is explained in withdraw or amend a building application.

FAQ

Revoking or amending a building decision under section 68

Can a final building decision be revoked at any time? +

No. Section 68 sets special conditions and distinguishes decisions without acquired rights, exceptional danger or economic situations, and statutory grounds of nullity. Finality remains the starting point.

Can an affected person demand action under section 68? +

There is no right to have the power of amendment or revocation under subsections 2 to 4 exercised. An application may be rejected as res judicata outside the special cases. The authority must still classify the file and the statutory conditions correctly.

What if the building decision is not yet final? +

The first question is whether an appeal or another ordinary remedy is still available. The deadline, service and suspensive effect must be assessed within that procedure.

Is every unlawful building permit void? +

No. Subsection 4 covers only the listed grounds of nullity. An alleged error must be assigned to its legal ground and does not automatically lead to a declaration of nullity.

How is this different from a building-police order? +

Section 68 concerns correction of a decision. A building-police order responds to a concrete condition or works that may conflict with building-police law. Both issues can arise together but remain legally distinct.

Topics
Building decisionSection 68 AVGFinalityRevocationAmendmentBuilding proceedings

Defects, a remuneration dispute, looming litigation?

In construction law, deadlines and evidence decide. Call us directly or send an email, callback within one business day.

Contact

A direct line to the firm.

Address

BRANDAUER Rechtsanwälte GmbH Giselakai 51 5020 Salzburg