Building authority inspects an ongoing construction site: access and documents

Construction-site inspections in Salzburg: access, information and findings the building authority may request during the works.

BRANDAUER Rechtsanwälte
Your law firm

BRANDAUER Rechtsanwälte

Salzburg law firm for real estate, construction and corporate law

Every matter is handled by a coordinated team of lawyers, legal staff and specialists. In construction cases we look at contract, evidence, deadlines and commercial consequences together.

22 September 2026 · Mag. Bernhard Brandauer, Rechtsanwalt

In Salzburg, the building authority may inspect the execution of a construction measure during the works to determine whether it complies with building law and the building permit granted.

The affected parts of the site must be accessible for that purpose. The authority may request information from the persons named in section 11 BauPolG and, for special projects, require findings for checking structural strength or fire safety.

This article explains the practical preparation and distinguishes an inspection during the works from the completion notice connected with occupation.

Place your situation

How can an ongoing site inspection be prepared?

Three answers lead from general preparation to an orderly treatment of missing documents and possible deviations.

Already know you want to get in touch? Go straight to the enquiry form.

01 Question 1

Has the building authority announced an inspection of the site?

Section 15 BauPolG permits an inspection of the execution. Preparation therefore starts with the information requested and the documents that explain the current state of the works.

All paths at a glance

Overview of all answers.

01

Prepare before a specific appointment

Put the building permit, approved plans, later plan versions and the contact details of the people involved in the works in one file. Mark which parts are complete and where the current execution may differ from the original plan.

02

Prepare the inspection in an orderly way

Make practical access to all affected parts of the site possible and ensure that the people with the relevant technical knowledge can be reached. Assemble the requested documents and a short chronology of the works.

03

Classify gaps and deviations openly

Prepare a list of missing documents and compare every deviation with the relevant plan version. State precisely what has already been built, which information is missing and which question the authority needs to answer.

What the building authority may inspect on site

Section 15 paragraph 1 BauPolG authorises the building authority to inspect the execution of a construction measure for compliance with building law and the building permit granted. The reference point is therefore the current state of the works compared with the approved project.

The inspection is a separate stage of the building procedure. It addresses whether the works comply with the legal requirements while construction is in progress. It does not replace the notice of completion and occupation, and it does not automatically decide whether that notice is complete.

The statutory power is broadly framed. The authority’s officers must be given access to construction sites in all their parts at any time. Section 15 paragraph 1 therefore does not limit an inspection to one visible area. The precise subject still depends on the project and the authority’s approach.

Which information and findings may matter

The building authority may request information from the persons listed in section 11 BauPolG. Preparation should therefore identify who can explain the technical execution, who knows the plan status and who manages the building file. The separate article on the site manager in Salzburg deals with appointment and responsibility at the start of works.

During the inspection, keep the building permit, approved plans and understandable records of the current state available. These documents provide a practical basis for the discussion. Additional documents depend on the project, the permit and the specific request.

For a special type of construction measure, the authority may require the building owner to provide findings if it considers them necessary to check structural strength or fire safety. Section 15 paragraph 1 gives load tests as an example. Record the requested finding, the affected elements and the requested timing precisely.

How to prepare the inspection in practical terms

Start with a simple comparison: Which plan was approved, which part is complete and which works are still under way? Mark changes with the building element, date and document that records the change. This allows the information to distinguish the approved state, later planning and actual execution.

Also make safe practical access to the affected parts of the site possible. Preparation should not reduce the inspection to a representative room if other parts of the works are involved. Construction-site safety remains a separate question from the authority’s inspection power.

After the appointment, keep minutes of the persons present, information requested, documents handed over and specific findings. State only what was actually discussed or provided. A separate legal assessment can follow afterwards.

What to clarify when deviations are found

If the authority identifies a deviation, first clarify which part of the execution and which permit or rule are concerned. A general statement that the building is different says little about the next step. The element, plan version, state of execution and precise official finding matter.

Do not change the works prematurely before the finding and the related documents have been secured. Whether a change is permitted, requires an amendment to the filing or has another consequence depends on the case. An inspection during construction must be distinguished from a later procedure about a deviation from the plan.

Section 15 paragraph 2 BauPolG also contains a specific power concerning machines that cause unlawful noise. The authority may prohibit further use in the relevant construction measures where the statutory requirements are met. That possible measure concerns a specific noise situation and is separate from the general review of documents.

Checkpoints

Keep inspection and completion notice separate

The same site can raise several legally different questions.

Which question is currently central?
Situation Core question Useful preparation
Ongoing site inspection Does the execution comply with the rules and the building permit? Access, plan status and technically responsible contact persons
Official information request What can the persons named in section 11 BauPolG explain? Record the persons, responsibility and content of the discussion
Finding on strength or fire safety Is a special finding necessary because of the project’s nature? Document the request, affected elements and exact finding
Completion and occupation Can completion or occupation now be notified? Review completion documents separately under section 17 BauPolG

The legal consequence depends on the project, the plan status and the content of the official finding.

Process

Four steps for an orderly inspection

A clear chronology separates access, information, findings and later responses.

  1. 01
    Step 1

    Identify the subject

    Record the appointment, letter or official request with its date and content.

    Note which building section and which question are involved.

  2. 02
    Step 2

    Order the building file

    Match the permit, approved plans and current execution.

    Mark deviations, open points and the responsible contact person.

  3. 03
    Step 3

    Enable access and information

    Provide access to the affected parts and answer factually.

    Record which documents and information were actually provided.

  4. 04
    Step 4

    Secure the findings

    Document findings, further requests and possible next steps separately.

    Before changing the works or making statements, classify the specific finding.

Practical tip: Keep one file for each inspection with the permit, plan status, current state and meeting notes. If you want to discuss the effect of an official finding on your project, you can arrange an initial consultation. Receive new articles and legal updates through the BRANDaktuellen Rechtsnews.

FAQ

Inspection of an ongoing construction site in Salzburg

May the building authority enter a construction site at any time? +

Section 15 paragraph 1 BauPolG states that the authority’s officers must be given access to construction sites in all their parts at any time. The inspection concerns compliance with building law and the building permit granted.

Does an inspection have to be announced in advance? +

Section 15 paragraph 1 BauPolG does not state a general advance-notice period for the inspection power itself. The communication of a specific appointment can depend on the authority’s procedure and the project. Keep any letter or official request with its date and content.

What findings may the building authority require? +

For a special type of construction measure, the authority may require the building owner to provide findings when necessary to check structural strength or fire safety. Section 15 paragraph 1 gives load tests as an example. The exact finding must be classified by its content and the affected elements.

Topics
Building authoritySite inspectionBauPolGBuilding permitConstruction worksDocuments

Defects, a remuneration dispute, looming litigation?

In construction law, deadlines and evidence decide. Call us directly or send an email, callback within one business day.

Contact

A direct line to the firm.

Address

BRANDAUER Rechtsanwälte GmbH Giselakai 51 5020 Salzburg